No, I don't think so. It's mid Sept. and they still have a few pre-production 4 seaters to build. Then they need to test the 10 pre-production cars. 1 month? 2 months? I don't know.
Then they're going to start building production units. They're going to build 400 4 seaters in the first batch, then 400 4 seaters in the second batch. Those are going to the first 800 customers who pre-ordered 4 seaters. Then they're going to build some of the El Diablos, but I don't remember if it's going to be 200 or 400 of those, then they'll switch back to making 4 seaters again.
My point is, they've pre-sold something like 3,000 units to customers who paid deposits and those are going to be built and delivered in roughly the order the deposits were made, in batches of 400 at a time. There is no way they're going to deliver any units under SN 3000 to a dealership that is taking the order now.
I feel they will deliver some units before the end of the year, but I'd be surprised if any are delivered in Nov. and certainly not one that was ordered now.